Every AI compute deal, in one sourced ledger

The contracts behind AI capex: 82 deals from Jan 2023 to Nov 2026, newest first, every number linked to the filing, release or report it came from. OpenAI is the buyer in 21, Anthropic in 14, Meta in 10.

82 of 82 deals$2.42T stated value in 4874.3 GW stated capacity in 32

DealChipsDetails
MicrosoftOracleMicrosoft winds down its Oracle AI cloud capacity rentaln/d–Older-generation NVIDIA GPUs–cancelled
AnthropicGoogle CloudAnthropic's $121.3B minimum Google Cloud TPU hosting commitment$121.3B1–Google TPU7signed
SpaceX (SpaceXAI, formerly xAI)Apollo Global Management (managed lessor entity)SpaceX (xAI) ~$40B GPU finance lease with Apollo-managed lessor$40B1–GPU pods (model not disclosed)5signed
GoogleConstellation EnergyGoogle–Constellation 20-year PPA backing 890 MW of nuclear upratesn/d––20signed
AmazonConstellation EnergyAmazon–Constellation 20-year, 690 MW Calvert Cliffs nuclear PPAn/d––20signed
AnthropicOnePWR SolutionsAnthropic–OnePWR $3.4B gas generators (1.7 GW)$3.4B1–––signed
UndisclosedSpaceX (xAI compute)SpaceX hosting deal worth $1.11B a month (customer undisclosed)n/d–––signed
FigureNscaleFigure–Nscale $3.5B compute deal (up to 100,000 Vera Rubin GPUs)$3.5B1–NVIDIA Vera Rubin–signed
AnthropicLambdaAnthropic–Lambda compute agreements (~$41.3B)$41.3B1–NVIDIA–signed
AnthropicNscaleAnthropic–Nscale GPU services agreements (up to ~$44.6B)≠$44.6B10.461NVIDIA–signed
OpenAISB EnergyNVIDIA guarantees up to $105B of OpenAI leases at SB Energy's PORTS campus (4.25 GW)$105B14.251NVIDIA20signed
AnthropicAMDAnthropic–AMD: up to 2 GW of MI450 Helios racks; AMD invests up to $5B$20B121AMD Instinct MI450 (Helios)–signed
Undisclosed AI developersIRENIREN signs $2.8B of new multi-year AI cloud contracts$2.8B1–––signed
Undisclosed hyperscalerApplied DigitalApplied Digital 210 MW, 15-year Delta Forge 2 lease with a hyperscaler$5.2B10.211–15signed
GoogleSpaceX (SpaceXAI, formerly xAI)Google rents ~110,000 NVIDIA GPUs from SpaceX at $920M a monthn/d–NVIDIA–signed
AnthropicSpaceX (SpaceXAI, formerly xAI)Anthropic rents SpaceX's Colossus compute (up to $120.5B through 2029)≠$120.5B10.31NVIDIA (H100, GB200 and later)–expanded
AnthropicAmazon (AWS)Anthropic commits $110B+ to AWS; Amazon invests up to $25B more$110B151AWS Trainium2–Trainium4, Graviton10signed
Jane StreetCoreWeaveJane Street–CoreWeave ~$6B AI cloud commitment$6B1–NVIDIA Vera Rubin–expanded
AnthropicCoreWeaveAnthropic–CoreWeave multi-year cloud agreementn/d–––signed
MetaCoreWeaveMeta–CoreWeave expanded deal (~$21B through 2032)$21B1–NVIDIA Vera Rubin–expanded
AnthropicGoogle; BroadcomAnthropic–Google–Broadcom multi-gigawatt TPU deal from 2027n/d3.51Google TPU (next generation)–signed
MetaNebiusMeta–Nebius five-year Vera Rubin deal (up to ~$27B)$27B1–NVIDIA Vera Rubin5signed
OpenAIAmazon (AWS)Amazon invests $50B in OpenAI; AWS deal expanded by $100B$100B121AWS Trainium3, Trainium48expanded
OpenAINVIDIANVIDIA invests $30B in OpenAI's $110B round$30B1–NVIDIA Vera Rubin–signed
MetaAMDMeta–AMD 6 GW GPU deal with 160M-share warrantn/d61AMD Instinct MI450–signed
MetaNVIDIAMeta–NVIDIA multiyear deal for Blackwell, Rubin GPUs and Grace CPUsn/d–NVIDIA Blackwell (GB300), Rubin, Grace, Vera; Spectrum-X–signed
NVIDIACoreWeaveNVIDIA invests $2B in CoreWeave; 5 GW AI factory framework$2B151NVIDIA–completed
OpenAICerebrasOpenAI–Cerebras 750 MW inference compute (over $10B)≠$20B10.751Cerebras wafer-scale engine–signed
MetaOracleMeta–Oracle cloud commitment (reported ~$20B)n/d–––signed
HUMAINAMDAMD, Cisco and HUMAIN joint venture (up to 1 GW by 2030)n/d11AMD Instinct MI450–expanded
HUMAINNVIDIAHUMAIN expands NVIDIA deal to up to 600,000 GPUsn/d–NVIDIA GB300 and later platforms3expanded
xAIHUMAINxAI–HUMAIN 500 MW+ data center in Saudi Arabian/d0.51NVIDIA GB300–announced
AnthropicMicrosoft (Azure)Anthropic–Microsoft–NVIDIA: $30B Azure commitment, up to $15B investment$30B111NVIDIA Grace Blackwell, Vera Rubin–expanded
AnthropicFluidstackAnthropic $50B US data centers with Fluidstack$50B1–––signed
MetaNebiusMeta–Nebius five-year GPU clusters (~$3B)≠$2.9B1––5expanded
Amazon (AWS)Cipher MiningAWS–Cipher Mining $5.5B 15-year lease (300 MW)$5.5B10.31–15signed
MicrosoftIRENMicrosoft–IREN $9.7B GB300 cloud contract$9.7B10.21NVIDIA GB3005signed
MicrosoftLambdaMicrosoft–Lambda multibillion-dollar GPU dealn/d–NVIDIA GB300 NVL72–signed
OpenAIAmazon (AWS)OpenAI–AWS $38B seven-year compute deal$38B1–NVIDIA GB200, GB3007expanded
OpenAIMicrosoft (Azure)OpenAI–Microsoft recapitalization: $250B incremental Azure commitment$250B1–––signed
GoogleNextEra EnergyGoogle–NextEra 25-year PPA to restart Duane Arnold nuclear plantn/d––25signed
AnthropicGoogle CloudAnthropic–Google Cloud up to 1 million TPUsn/d11Google TPU (Ironwood)–expanded
MetaBlue Owl Capital (JV)Meta–Blue Owl $27B Hyperion data center joint venture≠$27B1–––signed
MicrosoftNscaleMicrosoft–Nscale ~200,000 NVIDIA GB300 GPUs (US and Europe)n/d–NVIDIA GB300–signed
OracleAMDOracle–AMD 50,000 MI450 GPU superclustern/d–AMD Instinct MI450–announced
OpenAIBroadcomOpenAI–Broadcom 10 GW custom acceleratorsn/d101OpenAI-designed accelerator (Broadcom)–announced
xAISPV (NVIDIA GPUs)xAI $20B GPU financing via SPV for Colossus 2 (NVIDIA-backed)$20B1–NVIDIA5announced
OpenAIAMDOpenAI–AMD 6 GW GPU deal with 160M-share warrantn/d61AMD Instinct MI450–signed
OpenAISamsung Electronics; SK hynixSamsung and SK hynix join Stargate (DRAM supply LOIs)n/d–HBM / DRAM–announced
MetaCoreWeaveMeta–CoreWeave order (up to $14.2B through 2031)$14.2B1–––expanded
FluidstackCipher MiningCipher Mining–Fluidstack 168 MW Barber Lake lease, Google backstop$3B10.1681–10expanded
OpenAICoreWeaveOpenAI–CoreWeave expansion (up to $6.5B; $22.4B total)$6.5B1–––expanded
OpenAIOracle; SoftBank (SB Energy)Stargate adds five US sites (nearly 7 GW planned)$400B171–3expanded
OpenAINVIDIAOpenAI–NVIDIA 10 GW letter of intent (up to $100B investment)$100B1101NVIDIA Vera Rubin–announced
OpenAINscaleStargate UK (Nscale, OpenAI, NVIDIA)n/d–NVIDIA–announced
NVIDIACoreWeaveNVIDIA–CoreWeave $6.3B unused-capacity order$6.3B1–NVIDIA–signed
MicrosoftNebiusMicrosoft–Nebius GPU capacity from Vineland, NJ$17.4B1––5signed
MetaGoogle CloudMeta–Google Cloud six-year deal (over $10B)$10B1––6signed
FluidstackTeraWulfTeraWulf–Fluidstack 200 MW hosting, Google backstop$3.7B10.21–10expanded
CoreWeaveGalaxy DigitalCoreWeave takes the rest of Helios (526 MW critical IT in total)n/d0.1331–15signed
OpenAINscaleStargate Norway (Nscale, Aker, OpenAI) in Narvikn/d0.231NVIDIA–announced
OpenAIOracleOpenAI–Oracle 4.5 GW Stargate capacity≠n/d4.51NVIDIA–signed
CoreWeaveCore ScientificCoreWeave's $9B all-stock bid for Core Scientific (rejected)$9B1–––cancelled
Undisclosed (reported as OpenAI)OracleOracle discloses cloud contract worth over $30B a year from FY2028≠$30B1–––signed
Amazon (AWS)Talen EnergyAmazon–Talen 1,920 MW nuclear supply from Susquehanna$18B1–––expanded
MetaConstellation EnergyMeta–Constellation 20-year PPA for Clinton nuclear plantn/d––20signed
CoreWeaveApplied DigitalApplied Digital–CoreWeave 15-year leases at Polaris Forge 1$7B10.251–15expanded
OpenAIG42Stargate UAE 1 GW cluster (G42, OpenAI, Oracle, NVIDIA, Cisco, SoftBank)n/d11NVIDIA GB300–announced
OpenAICoreWeaveOpenAI–CoreWeave expansion (up to $4B)$4B1––4expanded
HUMAINAMDAMD–HUMAIN $10B collaboration (500 MW over five years)$10B10.51AMD Instinct GPUs, EPYC CPUs5expanded
CoreWeaveGalaxy DigitalCoreWeave exercises 260 MW Helios Phase II option$10.4B10.261–15expanded
HUMAINNVIDIAHUMAIN–NVIDIA AI factories in Saudi Arabia (up to 500 MW)n/d0.51NVIDIA GB3005expanded
CoreWeaveGalaxy DigitalCoreWeave–Galaxy Digital 15-year, 133 MW Helios leasen/d0.1331–15expanded
OpenAICoreWeaveOpenAI–CoreWeave initial cloud contract (up to $11.9B)$11.9B1––5expanded
OpenAIStargate LLC (SoftBank, OpenAI, Oracle, MGX)Stargate Project launch (OpenAI, SoftBank, Oracle, MGX)$500B1–NVIDIA4announced
AnthropicAmazon (AWS)Amazon adds $4B to Anthropic; AWS becomes primary training partner$4B1–AWS Trainium2–completed
GoogleKairos PowerGoogle–Kairos Power 500 MW small modular reactor fleetn/d–––signed
MicrosoftConstellation EnergyMicrosoft–Constellation 20-year PPA to restart Three Mile Island Unit 1n/d––20signed
MicrosoftBrookfield RenewableMicrosoft–Brookfield 10.5 GW renewable energy frameworkn/d––5signed
G42MicrosoftMicrosoft invests $1.5B in G42$1.5B1–––completed
AnthropicAmazon (AWS)Amazon invests up to $4B in Anthropic; AWS becomes primary cloud$4B1–AWS Trainium, AWS Inferentia–completed
OpenAIMicrosoftMicrosoft extends OpenAI partnership (third investment)n/d–––expanded

1 opens the source for that number. ≠ marks a figure that named sources report differently; the row note gives both. n/d means the parties have not disclosed it. Download: CSV · JSON (CC BY 4.0)

Who is buying compute

All 41 companies
  1. OpenAI 21 deals $1.6T
  2. Anthropic 14 deals $549.1B
  3. CoreWeave 14 deals $89.3B
  4. Microsoft 11 deals $308.6B
  5. Meta 10 deals $102.1B
  6. Amazon 8 deals $279.5B
  7. Google 8 deals $131.3B
  8. NVIDIA 7 deals $138.3B
  9. AMD 6 deals $30B
  10. Oracle 6 deals $430B

Built to be cited

Methodology

Filings first. An SEC 8-K, 10-Q or 6-K beats a company release, and a company release beats a press report. 46 rows rest on a filing; 136 sources back the ledger in total, each with the date we read it.

Conflicts stay visible. When early reports say more than $10 billion and Cerebras’s IPO prospectus says more than $20 billion, the row carries the filing’s number and a note naming both. Expansions and cancellations get their own rows, so a relationship’s history reads top to bottom.

Free to reuse. The whole ledger is open data under CC BY 4.0: CSV, JSON and llms.txt. Credit “AI Compute Deals (aicomputedeals.com)” and link the row you cite.

The questions behind the headlines

How big is the OpenAI–Oracle deal?

OpenAI and Oracle agreed on 22 July 2025 to develop 4.5 GW of additional Stargate capacity in the US (ledger row, Built In). Oracle’s 30 June 2025 8-K disclosed a contract worth more than $30 billion a year from fiscal 2028 (ledger row, Oracle 8-K). The Wall Street Journal put the total at $300 billion over about five years from 2027 (Built In, citing WSJ). Neither company has confirmed the $300 billion figure.

How much compute has OpenAI committed to buy?

About $730 billion in contracted or reported cloud commitments: Microsoft Azure $250B (Microsoft), Oracle about $300B (reported), AWS $38B plus a $100B expansion (Amazon 8-K), CoreWeave about $22.4B (CoreWeave) and Cerebras over $20B (Cerebras prospectus). On top come chip deals sized in gigawatts with no price disclosed: NVIDIA 10 GW, AMD 6 GW and Broadcom 10 GW. Every OpenAI deal

Did NVIDIA invest $100 billion in OpenAI?

No. In September 2025 the two signed a letter of intent: NVIDIA would invest up to $100 billion, paid as each gigawatt of a 10 GW buildout came online (NVIDIA). Letters of intent are generally not binding (DCD). In February 2026 NVIDIA put $30 billion into OpenAI’s funding round instead (ledger row, Built In).

Where does Anthropic get its compute?

From ten suppliers, and its IPO filing puts numbers on the biggest (Anthropic S-1/A). Google Cloud: at least $121.3B of TPU hosting through July 2033, plus TPU capacity from Broadcom (ledger row). SpaceX: up to $120.5B for Colossus GPU capacity through 2029 (ledger row). Amazon: at least $110B on AWS Trainium through April 2036 (ledger row). Microsoft Azure: at least $44.9B through June 2033. Nscale up to about $44.6B, Lambda about $41.3B, and AMD more than $20B for MI450 Helios racks. CoreWeave and Fluidstack add capacity on top. Every Anthropic deal

What is a backstop in an AI compute deal?

A guarantee from a large company that a smaller party’s lease or capacity will be paid for, which lets the smaller party borrow against the contract. Google backstopped $1.8B of Fluidstack’s lease at TeraWulf (TeraWulf 8-K) and $1.4B at Cipher Mining (Cipher 8-K). NVIDIA agreed to buy any capacity CoreWeave’s customers leave unused through April 2032, in a $6.3B order (CoreWeave 8-K). All backstop deals