Google AI compute deals
Google is party to 8 deals in the ledger, buyer in 4 and seller in 4. The 2 with a stated price add up to $131.3B in headline value. Stated capacity: 4.5 GW. Counterparties: Anthropic, Constellation Energy, SpaceX, NextEra Energy, Meta, Kairos Power.
Verified 9 Nov 2026. Sums count each row’s headline figure as stated, cancelled deals excluded. Open in the full ledger
-
Anthropic's $121.3B minimum Google Cloud TPU hosting commitment
Sells to Anthropic
Minimum spend of about $121.3 billion, April 2026–July 2033, with a true-up (S-1/A). Signed March 2026 and amended May–Oct 2026; first disclosed in the S-1 filed 26 Oct 2026. Excludes an estimated $125–150 billion for additional TPU compute in 2028–2031. Likely overlaps the April 2026 Google–Broadcom TPU announcement.
$121.3B1 signed -
Google–Constellation 20-year PPA backing 890 MW of nuclear uprates
Buys from Constellation Energy
Contract value not disclosed; $4.3 billion+ is Constellation's planned investment. Plant size: about 890 MW of new uprate capacity across 11 units, plus a separate 15-year 2,700 MW energy agreement.
n/d signed -
Google rents ~110,000 NVIDIA GPUs from SpaceX at $920M a month
Buys from SpaceX (SpaceXAI, formerly xAI)
$920 million per month from Oct 2026 through June 2029 (roughly $30 billion if it runs the full term). Google may exit or take a pro-rata cut if SpaceX misses the 30 Sept 2026 delivery date; after 31 Dec 2026 either party may end it on 90 days' notice.
n/d signed -
Anthropic–Google–Broadcom multi-gigawatt TPU deal from 2027
Sells to Anthropic
Not disclosed. Broadcom's 8-K (6 Apr 2026): about 3.5 GW from 2027, dependent on Anthropic's continued commercial success. Anthropic's S-1/A lists five-year Broadcom equipment leases for TPU capacity with rent of about $161.2 billion in total (all Broadcom leases, not only this deal).
n/d 3.5 GW signed -
Google–NextEra 25-year PPA to restart Duane Arnold nuclear plant
Buys from NextEra Energy
0.615 GW plant (Duane Arnold Energy Center restart); Google buys its output, not delivered data center capacity. Financial terms not disclosed.
n/d signed -
Meta–Google Cloud six-year deal (over $10B)
Sells to Meta
"More than $10 billion" over six years, per The Information, confirmed to AFP by a source. Not disclosed by the companies.
$10B1 signed -
Google–Kairos Power 500 MW small modular reactor fleet
Buys from Kairos Power
0.5 GW of planned small modular reactor output from seven reactors; generation bought by Google, not delivered data center capacity. Financial terms not disclosed. First project (Hermes 2, up to 50 MW, sold via TVA) announced Aug 2025.
n/d signed